  • The supply of wind turbines and tower equipment required for the H17# site of this project is planned to be completed in October 2023
  • Three Gorges Energy Jiangsu Dafeng 800MW offshore wind power project is located in the northeastern waters of Dafeng District, Yancheng City
Reading this article requires
5 Minute

Recently, the winning bid results for the procurement of wind turbine units and tower equipment for the Jiangsu Dafeng 800MW offshore wind power project were announced. Goldwind Technology won the bid with a winning price of 3.083 billion yuan.

Bidding scope: The procurement scope of this bidding includes the offshore wind turbines, towers, ancillary equipment and supporting services required for the project, with a total procurement capacity of 800MW. This project plans to use offshore wind turbines with 8.5MW ≥ single unit capacity ≥ 6MW (mixed operation is accepted, and the number of mixed units is no more than two). In addition to the above models, up to one large-capacity unit (single unit capacity 12MW and above) can be used. ) test model; the total installed capacity is allowed to increase by less than the capacity of one bidding model (minimum bidding model).

Delivery plan: The supply of wind turbines and tower equipment required for the H17# site of this project is planned to be completed in October 2023, and the supply of wind turbines and tower equipment required for the H8-1#, H9#, and H15# sites is planned to be completed in May 2024. Complete supply.

It is understood that Three Gorges Energy Jiangsu Dafeng 800MW offshore wind power project is located in the northeastern waters of Dafeng District, Yancheng City, and includes 4 sites:

The Dafeng H8-1# site is 80km offshore, with a water depth of 9~18m, a planned sea area of 32km², and a planned installed capacity of 200,000 kilowatts; the Dafeng H9# site is 75km offshore, with a water depth of 7~15m, and a planned sea area The area is 29km², and the planned installed capacity is 200,000 kilowatts; the Dafeng H15# site, the offshore distance is 71km, the water depth is 7~15m, the planned sea area is 29km², and the planned installed capacity is 200,000kilowatts; the Dafeng H17# site, the offshore distance is 47km , the water depth is 0~15m, the planned sea area is 31km², and the planned installed capacity is 200,000 kilowatts. Editor/Xu Shengpeng